A personĀ X can complete 20% of work in 8 days and another person Y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work by completed?

  1. 6
  2. 8
  3. 10
  4. 12
  • Answer: The correct option is A
  • Explanation:

    X can complete 20% of work in 8 days. So, he will complete 100% work in 40 days.

    Similarly, Y can complete 25% of work in 6 days. So, he will complete 100% work in 24 days.

    In 1 day, the amount of work they will complete while working together = 1/40 + 1/24

    = (3 + 5)/120 = 8/120 = 1/15

    So, they need 15 days to complete the whole work.

    Time needed to complete 40% of the work = 40% of 15 = 6 days.