A person X can complete 20% of work in 8 days
A personĀ X can complete 20% of work in 8 days and another person Y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work by completed?
- 6
- 8
- 10
- 12
- Answer: The correct option is A
- Explanation:
X can complete 20% of work in 8 days. So, he will complete 100% work in 40 days.
Similarly, Y can complete 25% of work in 6 days. So, he will complete 100% work in 24 days.
In 1 day, the amount of work they will complete while working together = 1/40 + 1/24
= (3 + 5)/120 = 8/120 = 1/15
So, they need 15 days to complete the whole work.
Time needed to complete 40% of the work = 40% of 15 = 6 days.